Lead2pass 70-178 material details are researched and created by the most professional certified authors who are regularly using current exams experience to create precise and logical dumps. You can get questions and answers from many other websites or books, but logic is the main key of success. And Lead2pass will give you this key of success.
QUESTION 71
You are building a project plan in Microsoft Office Project Standard 2010.
You expand the project plan to display all outline levels and the project summary task.
You enter resources and their costs.
You have not yet set a baseline.
You need to estimate the total cost of the project.
What should you do?